Installation of Air Circuit Breakers - Schedule of retrofitting

Dear Residents,
 

 
We thank you for your kind support extended during last Sunday's ESS2 shutdown. Please note we have reached the fifth & last scheduled shutdown towards modifications of our LT Panel ACB retrofitting job.
 

 
Please note on next Sunday, 27th September 2020, we will be having 4000 Amps ACB replacement activity scheduled in ESS 1 along with bus bar modifications of the concerned sections. Please note the below schedule for your perusal:
 

 
ESS 1 LT Panel ( 4000 Amp ACB section # 01) :
 

 
Impact Towers/ areas - Genex, Mark, Oscar & Market Area
 
Timing - 1000 hrs to 2000 hrs
 
Power status - No DG / No Grid
 

 
Complete bus bar modification to be done in this section to retrofit the new 4000 Amp ABB make ACB & hence we need extended shutdown time. We will try our best to power up the market complex through a temporary circuit so that essential supplies of medicines, life saving drugs, insulin & milk etc are not disturbed.
 

 
Other towers & Pump Room:
 

 
Rest other AT towers, Mantova, Siena, BT Towers, Club & AT/BT Pump Room will not be affected during the above said shutdown.
 

 
Main 33kV HT Distribution Panel :
 

 
We will be working in the main 33kV HT Distribution Panel located at ESS 1 as well to do certain transformer HT XLPE cabling jobs. This will enable us to make all 04 transformers operational in ESS1. During this period the entire society will be on DG Power from 1000 hrs to 1430 hrs as we will be shutting down Grid power for safety reasons.
 

 
We understand the pain & discomfort faced by residents during these shutdowns in this weather. Since this is the last one towards improvement of our LT side infra restoration, we solicit your kind cooperation in this regard.
 

 
Regards,
 
Omaxe Heights (Faridabad) Resident Welfare Association®
 
Please visit our website http://www.omaxeheightsrwa.org